Virginia Reviews High-Voltage Transmission Proposal Amid Rising Electricity Demand

Dominion Energy’s proposed Morrisville-to-Wishing Star electric transmission project has reached a key stage in Virginia’s regulatory review process, with a public evidentiary hearing scheduled to begin November 16, 2026. The project would expand high-voltage transmission infrastructure across Fauquier, Prince William and Loudoun counties, supporting electricity reliability and growing demand throughout Northern Virginia. The Virginia State Corporation Commission (SCC) is reviewing the proposal to determine whether the planned facilities meet regional electricity needs and applicable siting requirements.

The proposed project includes approximately 36.5 miles of new 500-kilovolt (kV) transmission lines along or near existing utility rights-of-way, an additional 230-kV transmission line in Fauquier County and expansion of the existing Morrisville Substation. The improvements are intended to strengthen the regional transmission network, increase system capacity and support the continued delivery of electricity to residential, commercial and industrial customers. Dominion Energy has identified a preferred transmission route while also evaluating alternatives based on engineering requirements, existing infrastructure and potential community impacts.

According to Dominion Energy, regional electricity demand has increased substantially since the existing transmission corridor was upgraded in 2008. The utility identifies continued development, including the expansion of data center facilities, as a contributing factor in projected electricity requirements. Northern Virginia has experienced significant growth in data center infrastructure, creating additional demand for transmission capacity and related utility improvements. The proposed transmission facilities are intended to address current and anticipated capacity needs while maintaining system reliability.

The project also involves extensive planning related to transmission line routing, land use and construction methods. Dominion Energy has evaluated options for expanding existing utility corridors, rebuilding portions of the current transmission system and establishing alternative routes where existing development or engineering constraints limit available space. The company has also considered environmental and historic preservation requirements, including potential impacts near Manassas National Battlefield Park. These considerations form part of the ongoing review of the project’s proposed alignment and construction approach.

Dominion Energy submitted its application to the Virginia SCC on February 27, 2026, under Case No. PUR-2026-00021. The commission subsequently established a procedural schedule that included public participation, testimony from interested parties and regulatory staff review. The November 16 evidentiary hearing is scheduled to continue on additional dates through November 24, if necessary. The SCC is responsible for evaluating the project’s necessity, proposed transmission routes, structures and relevant environmental considerations before issuing a decision.

Under Dominion Energy’s preliminary schedule, construction could begin in spring 2027, with completion anticipated in summer 2030. These dates remain dependent on regulatory approvals, final engineering, permitting and construction planning. The company has continued public outreach throughout the development process, including community meetings and opportunities for residents and stakeholders to review proposed routes and provide feedback.

The Morrisville-to-Wishing Star proposal reflects the relationship between regional electricity demand, utility infrastructure planning and transmission system development. As Northern Virginia continues to accommodate new commercial and industrial electricity requirements, transmission projects of this scale involve coordination among utilities, regulators, local governments and affected communities. The SCC’s review will help determine the project’s final configuration and whether the proposed infrastructure improvements can proceed toward construction.