|
|
| |
| |
 |
|
| |
Signature Mississippi Bridge receives a $640 million solution. By Andrew Gates
When U.S. Secretary of Transportation
Ray LaHood, joined by a dozen
federal, state and local officials,
shoveled Illinois and Missouri soil
together to start construction on the
New Mississippi River Bridge in St. Louis, it was more
than just a celebration. It was a symbol of nearly 20
years of cooperation, commitment and compromise
needed to address a growing regional transportation
need in the greater St. Louis metropolitan area.
In 1992, regional officials identified a new river
crossing as one of the largest infrastructure needs
in the St. Louis region, an area encompassing three
counties in Illinois and four in Missouri. This new
bridge is needed because of congestion on the Poplar
Street Bridge, or PSB, crossing the Mississippi. The
PSB is a major transportation artery across the river.
It carries three interstates (I-70, I-55 and I-64) and
currently has too much traffic on it. Bringing three
major interstates across one bridge creates a natural
chokepoint for the region. A crash or maintenance work on the bridge can create backups for miles.
Studies determined conditions on the PSB would get
worse as traffic levels continued to increase. Traffic
engineers predicted that PSB traffic levels would
rise to more than 150,000 vehicles daily by 2030 if
nothing was done.
"The regional transportation planning organization
commissioned a study and determined that the best
way to improve traffic flow in the region was to build
a new bridge across the Mississippi and to relocate
I-70 onto that new bridge," said Greg Horn, P.E.,
New Mississippi River Bridge Project Director. "The
two state departments of transportation started work
to determine the location and the environmental
impacts for a new bridge."
That location study was finished in 2001. The
conceptual design for the new crossing, based on that
study was a 2,000 foot, eight-lane main span cablestayed
bridge with 500 foot towers about a mile north of
the Poplar Street Bridge. This design included a number
of other improvements to keep regional traffic flowing.
|
|
| |
 |
|
| |
"It was a symbol of nearly 20 years of
cooperation, commitment and compromise
needed to address a growing regional
transportation need in the greater St. Louis
metropolitan area." |
|
| |
The price tag on the new bridge was roughly $2
billion _ much more than both states could afford
even for a project with such regional impact as this.
"We had to look at how we could cut costs to make
this bridge more affordable, so we started redesign
work to reduce costs," Horn said.
The next conceptual design, completed in 2005,
was estimated to cost about $1 billion. Even with a
2005 Federal Transportation Bill appropriation of
$239 million _ the largest appropriation ever for a
single project _ the two states were still unable to put
together funding for a new bridge. "From that point,
the two states worked together to determine how to pay
for this bridge project," said Horn. "Both states brought
forth proposals to the table. We looked at establishing
a public-private partnership that would charge tolls; we
looked at a companion bridge project for another local
bridge; and we looked at different locations and a variety
of other options."
Finally, in early 2008, the two states came to a $640 |
|
million solution that met the regional needs and could
be funded. The solution was to build this project in
phases. The first phase would construct a four-lane,
1,500-foot span bridge that can be expanded to six lanes
by restriping in the future as traffic levels demand. This
project should adequately handle traffic for the next 20
years, and it is also being designed to be compatible with
a future companion bridge (the second phase), which
will add another four lanes when traffic demands and
more funding are available.
As part of the bi-state agreement, Missouri would
manage the design and construction of the river
crossing. Each state would take responsibility for
the construction on their side of the river. Illinois
committed $313 million for their portion of the
bridge and three miles of roadwork on their side of
the river. Missouri committed $88 million for their
share of the bridge and one-half mile of roadwork on
their side of the river. By including the $239 million
Federal appropriation, the two states could fund the |
|
| |
 |
|
| |
project and start design work.
With funding in place, the process to design and
start construction on the bridge project was fraught
with its own challenges. One of the biggest was
the numerous agreements with railroad partners on
the project _ five in Illinois and one in Missouri.
"The Illinois Approach, the section of bridge
leading up to the main bridge, spans 17 tracks,"
said Gwen Lagemann, P.E., Illinois Department of
Transportation programming engineer for the New
Mississippi River Bridge. "Each of the 11 piers is
on railroad property. We worked closely with the
railroads for more than two years to make sure our
design was acceptable to all parties."
Besides coordination with the railroads, the
project management had to coordinate four major
sections of the project. These sections were natural |
|
breaks in the project and included: the cable-stayed
bridge; the Missouri interchange; the Illinois trilevel
interchange at I-55, I-64 and I-70; and the
connection between that Illinois interchange and the
bridge. During design, Illinois added $60 million
for an interchange between the I-70 connection
and Illinois Route 3. Due to size and complexity,
each section was designed by a different firm, which
meant that adjustments on one project needed to be
communicated quickly with the firm working on
adjoining sections.
"One of the biggest successes during this project was
having a co-located office to design the cable-stayed
bridge and the approaches," said Horn. "We had many
of the major players together in one location: HNTB, |
|
| |
 |
|
| |
who designed the cable-stayed bridge; CMT, who
designed the Missouri interchange; MODOT; IDOT;
Federal Highway; and many of the subcontracted
design firms. That way, when we had a design issue,
our engineers could talk to each other quickly. We
didn't need to set up special meeting times or leave
messages. This helped us design an effective bridge
quickly and efficiently."
Bids on the cable-stayed came in $40 million
more than the expected amount, due to the risks of
constructing this major river bridge. Fortunately,
since bids on many other elements came in below
projections, the overall corridor should remain within
budget. Current plans for the bridge construction call
for the project to be complete and traffic on the new |
|
bridge in 2014 _ four years from the date leaders
from two states joined forces to break ground. Crews
are currently on the river completing underwater
foundation work.
The challenges and the partners have changed, to
include the rise and fall of the level of the mighty
Mississippi, but all team members are committed to
ensuring that through cooperation and compromise, the
greater St. Louis metropolitan region will have a new
landmark gateway through the heartland of America. |
|
| |
|
|
Andrew Gates has been mayor of New York City
since 2002. For more information,
visit andrew.gates@modot.mo.gov.
|
|
| |
|
|
|
|
|
|
|